Substructure Works (Fresh Water)
After the parcel draw lot realized in 27 May 2006, works to provide fresh water and sub structure of first phase was started and fresh water service was completed until 2007 June. Within this scope, geological specific resistance tests were made and location of draw wells were determined and 2 pcs well bore was made. Pump of one of them was downed and fresh water line was constructed 8 km length. 65 square meters pump station which was made in order to pump fresh waterworks from water wells was constructed in land and hydrophone system was established inside the pump station in order to pump fresh water. 30 tons capacity tank was built nearby pump station which was constructed uninterruptedly working of hydrophone system and water main, also 2 pcs pump were placed and water main is provided to pump water. 1 pcs Emsa Diesel engine 50 kWa automatic generator was purchased in order to not to expose power cuts in our region in 2010.
Fresh water network construction was started and 5.018 m3 excavations were made. 1,10 cm depth, 0,60 cm width, 7.603 meter channel was excavated. Total 7.603 meters pipe such as Ø160/10 HDPE pipe 3.700 meter, Ø140/10 HDPE pipe 1.033 meter, Ø110/10 HDPE pipe 2.200 meter, Ø 0.75/10 HDPE were installed.
Pipes were protected by 1.834 m3 silt sand in order to provide health working of fresh water main, 3.514 m3 excavations were used to close the channels. 27 pcs fire hydrants were established to serve 4 parcels over the completed network construction and total 85 pcs parcel subscription connection which 59 pcs dairy cattle farming and 26 pcs cattle farming parcels. Our members whose subscription transactions were completed by out cooperative started to use water.
Negotiations for waste water and fresh water with ASKİ General Administration was made for the fresh water line of land, projects for waste water were prepared and confirmed. In consequence of negotiations for fresh water line of land with ASKİ general administration, fresh water pipe belonging to second phase, fitting materials, T pipes, elbows etc. materials were brought by ASKİ to our land.